Project Charter
Project Title: J&J Social Networking for R&D
Prepared by: Sam Evans
Project Start Date: 1/23/12 Projected Finish Date: 4/27/12
Budget Information: $100,000
Project Manager: Lindsay Graffius, [email protected]
Project Objectives: Establishing a social network through which the research and development teams can collaborate on projects that are being worked on at Johnson and Johnson.
Main Project Success Criteria: The network must meet all requirements for forming a communication channel for the research and development teams. Create a detailed solution and implementation phase for the development of a social network.
Approach:
· Gain a basic understanding of the research and development process utilized in the pharmaceutical industry
· Propose a solution to Meagan and Eric customer profiles.
· Research and evaluate social networking technologies utilized in the work environment. Justify the solution approach via this evaluation and present findings to the project sponsor.
· Outline critical success factors and risks for this project, and incorporate into project plan appropriately.
· Create an intermediate presentation for I/T partners that will explain your approach and strategy.
· Final presentation for business partners that will explain the recommendations.
· Create a final report to document all findings.
Roles and Responsibilities:
Role Name Organization/Position Contact Information
Project Manager Lindsay Graffius IST302 [email protected]
Group Meeting Supervisor Alex Long IST302 [email protected]
Researcher Alex Celento IST302 [email protected]
Requirements Sam Evans IST302 [email protected]
Requirements Greg Wuss IST302 [email protected]
Charts/Diagrams Suaad Mohammed IST302 [email protected]
Sign-off:
Lindsay Graffius Samuel Evans
Alex Long Suaad Mohammed
Alex Celento Greg Wuss
Project Title: J&J Social Networking for R&D
Prepared by: Sam Evans
Project Start Date: 1/23/12 Projected Finish Date: 4/27/12
Budget Information: $100,000
Project Manager: Lindsay Graffius, [email protected]
Project Objectives: Establishing a social network through which the research and development teams can collaborate on projects that are being worked on at Johnson and Johnson.
Main Project Success Criteria: The network must meet all requirements for forming a communication channel for the research and development teams. Create a detailed solution and implementation phase for the development of a social network.
Approach:
· Gain a basic understanding of the research and development process utilized in the pharmaceutical industry
· Propose a solution to Meagan and Eric customer profiles.
· Research and evaluate social networking technologies utilized in the work environment. Justify the solution approach via this evaluation and present findings to the project sponsor.
· Outline critical success factors and risks for this project, and incorporate into project plan appropriately.
· Create an intermediate presentation for I/T partners that will explain your approach and strategy.
· Final presentation for business partners that will explain the recommendations.
· Create a final report to document all findings.
Roles and Responsibilities:
Role Name Organization/Position Contact Information
Project Manager Lindsay Graffius IST302 [email protected]
Group Meeting Supervisor Alex Long IST302 [email protected]
Researcher Alex Celento IST302 [email protected]
Requirements Sam Evans IST302 [email protected]
Requirements Greg Wuss IST302 [email protected]
Charts/Diagrams Suaad Mohammed IST302 [email protected]
Sign-off:
Lindsay Graffius Samuel Evans
Alex Long Suaad Mohammed
Alex Celento Greg Wuss
project_charter.docx | |
File Size: | 16 kb |